The reply to this letter is here.
_________________________________
To: Chief Executive
East Riding of Yorkshire Council
Dear Mr. Pearson,
We the
undersigned request that as the responsible planning authority,
the East Riding of Yorkshire Council immediately investigate the
breaches of the planning conditions detailed in the Notice of
Decision, report to the Planning Committee and in the meantime
stop any test drilling at Crawberry Hill until -
i) Rathlin give proof that they are fully compliant with planning conditions and ii) A detailed monitoring regime and schedule of inspection visits by the ERYC, Yorkshire Water and the Environment Agency is agreed and published. (References: Report to the Planning Committee ERYC 13th September 2012 Application for Construction of a temporary drilling site etc 12/02945/STPLF, and Notice of Decision, Town and Country Planning Act, 1990, |
1.Background to the this request
Unconventional High Volume, High Pressure Hydraulic Fracturing known as Fracking
1.1 Fracking at Crawberry Hill
A specific condition of the planning permission was included following representations from local residents,
15.Hydraulic fracturing (also known as “hydro-fracking” or “fracking”) is expressly not permitted under the development hereby approved.The condition is imposed in the interests of groundwater protection and the broader protection of the amenities of residents. (NOD Condition 15)
However, in a later application to the
Environment Agency submitted by Rathlin Energy UK Ltd on 16th
January 2014 it is stated that as part of the test drilling Rathlin
will
“inject liquids into the well….. for “well stimulation” or “hydraulic fracturing” purposes..” (Section 9.4.5 page 10)
In addition Rathlin state
The activity on site relates to the exploration for hydrocarbons from the Crawberry Hill 1 wellsite. Specifically, this will involve perforation of the existing well-casing to perform tests within the Bowland Shale, Namurian Sandstone and Kirkham Abbey formations. These tests may require the injection of water, some of which may return to the surface. (EA 9.2.1 page 8)
This is a reference to the exploratory
hydraulic fracturing of the Bowland shales used elsewhere in the UK
by companies such as Cuadrilla or I-gas who are open about their
search for shale gas in the same Bowland shales.
Mr Ian Crane, with 20 years experience as a
senior executive in the oil industry, is ready to give evidence that
the Bowland shales are known to be “tight”. Like similar gas
shales in the USA where fracking has been used extensively, gas can
only be extracted by hydraulic fracturing for testing and production
purposes.
Further understanding of Rathlin’s intentions
may be gained from the current installation of fracking pumps at the
West Newton test site.
In contrast to the statements by Rathlin as
part of public consultation and subsequently, the papers submitted by
Rathlin to the High Court hearing of 29th July 2014
included the lease agreement with Philip Ellerington which states
“Rathlin has an option at any time to require the Second Claimanat to grant Rathlin a lease of Crawberry Hill in order to construct and operate a long term production facility at Crawberry Hill. The lease would be for a term of 25 years with an option to renew for a further 25 years.”(Witness statement of Tom Selkirk. 22/07/2014. Para.6. Page 2. Copy attached)
Rathlin are not currently testing, including
the use of fracking, at Crawberry Hill but intend to do so now they
have possession of the site. They are therefore not currently in
breach of Condition 15 but are making preparation to do so.
Given the emerging data and analysis of long
term serious health impacts from fracking in the USA and the detailed
reports of the failure of hydraulic fracking at Preese Hall in 2011
we urge a review of the planning permission given to Rathlin because
of the risks posed to residents of the East Riding and refer to our
European Convention Human Right Article 8.
2. Groundwater Management
2.1 Breach of Planning Conditions 5.9 and 5.10
Condition 5.9. States
“There shall be no discharge of foul or contaminated drainage from the site into either the ground water or any surface waters, whether direct or via soakaways.” ( NOD page3)
Condition 5.10. States
“The drainage system of the bund shall be sealed with no discharge to any watercourse, land or underground strata. Associated pipework should be located above ground and protected from accidental damage. All filling points and tank overflow pipe outlets should be detailed to discharge into the bund.” (NOD page3)
The attached photograph shows there is no bund
on the eastern boundary of the main drilling site so if we experience
a severe weather event similar to recent storms in nearby Cottingham
or Market Weighton there would be a high probability of run-off onto
the pea and wheat crops in adjacent fields.(Attached A.0)
The photographs also show leakage from the
storage tank used to receive surplus water from the drainage ditches
on the drilling pad.(Attached 1-5) This leaks into a very small bund
around the tank which does not meet the specification of 110%
capacity of the tank.
While the current position is that rainwater is
likely to be the main run-off, the concern must be that without full
conformity with the planning permission and regular monitoring by the
planning authority (ERYC) , the Environment Agency and Yorkshire
Water, the commencement of drilling and testing does pose significant
risk to local crops and the aquifer.
The well testing will involve thousands of
gallons of hydrochloric acid and other chemicals. Rathlin’s
application to the Environment Agency acknowledges that drilling
fluids and any water released from deep underground by drilling will
be likely to contain Naturally Occurring Radioactive Materials
(NORMs) as well as solid radioactive scale from the equipment. It is
an obvious risk if spills and leaks mean that rainwater can wash
these contaminants onto farmland and into the aquifer.
(Such a spillage has already been reported
to Birds Eye, the buyer of the peas harvested at West Newton. Philip
Ellerington cites his contract with Birds Eye as the reason for
urgent repossession of his land in his High Court witness statement
dated 21/07/2014)
The Environment Agency, gave permission to
Rathlin to drill at Crawberry Hill on 2nd May 2014.
“These include a Permit (EPR/BB3000KC) for
mining waste operations at the wellsite, namely the management of
extractive waste from prospecting for mineral resources. The permit
also allows flaring of waste gas arising from onshore oil and gas
operations as Permit (PB3930DV) for disposal of radioactive waste.”
(Tom Selkirk. Witness statement 22/07/2014 Para 28. Pages 8 and 9)
Further detail about waste is given in
Rathlin’s application to the Environment Agency dated 16/01/2014.
9.2.1 How do you plan to accumulate radioactive waste?
The
activity on site relates to the exploration for hydrocarbons from
the Crawberry Hill 1 wellsite. Specifically, this will involve
perforation of the existing well-casing to perform tests within
the Bowland Shale, Namurian Sandstone and Kirkham Abbey
formations. These tests may require the injection of water, some
of which may return to the surface. Additionally, water naturally
present in the target formation has the potential to flow to the
surface. Contact with the target formations mean that waste
(produced water) may contain low levels of Naturally Occurring
Radioactive Material(NORM) and so accumulation of radioactive
waste is unavoidable. There is also potential for scales forming
within associated pipe network. The waste produced waters arriving
at the surface will be piped to a device which separate any
hydrocarbons present from the produced waters. The produced waters
will then be piped directly into, and accumulated in, dedicated
storage tanks, from which they are removed by road at suitable
intervals for disposal to an authorised waste disposal facility.
Equipment found to be contaminated with scales will be removed
from service and stored in a designated quarantine area to await
removal from site ( following characterisation).
|
The application goes on to request a maximum
storage period on site of 3 months while the waste is tested and
further indicates a maximum volume of waste storage of 125 cubic
metres.
(Crawberry Hill B9 Application Form
16/01/2014 9.2.2 and 9.2.3 page 8)
The volume of the current, leaking, storage
tank for groundwater is 24 cubic metres so Rathlin are requesting 5
similar storage tanks for radioactive waste.
2.2 Lack of routine monitoring at Crawberry Hill
The Protectors at Crawberry received a letter from Martin Christmas of the Environment Agency (attached A.1 ) and Mr Crane replied on the 22nd June ( attached A.2 ).
On the weekend of 19th-20th
July there was heavy rainfall. Mr Crane noted the water from the
drainage ditch on the well site was up to the level of the overflow
pipe. He opened the valve to drain some of the water in the ditch
into the overflow tank. It quickly became apparent that the 24 cubic
metre relief tank is not fit for purpose. The tank had a leak at the
base of the tank (photos attached A.3- A.5 ) and at the seal between
the overflow pipe and the tank.
Jon Mager contacted the Planning office on the
21st July to enquire about Crawberry Hill. He asked if the
case office, Shirley Ross, had visited the drilling site recently. He
was told that Mrs Ross was on leave and that the details of
monitoring visits were kept by her.
The water was leaking straight onto the soil so
Mr Crane shut off the overflow valve and tried to call Martin
Christmas at the Environment Agency. Martin Christmas returned the
call on the morning of Thursday 24th July (call recorded).
Having explained the situation regarding leaks Mr Crane invited him
to visit the Crawberry Hill site to conduct his own inspection;
Martin Christmas advised that he wasn’t too concerned because it
would only be rainwater.
On the 30th July Jon Mager contacted
Mrs Ross to catch up on planning issues on her return from leave. Mrs
Ross confirmed that she was responsible for monitoring but had not
visited for some while.
Mr Mager then outlined the concerns about
leaks; Mrs Ross replied that the Environment Agency carried out
regular checks and was surprised to be told that this was not the
case.
2.3 Summary
In summary Rathlin have not conformed to the strict conditions laid down to ensure that groundwater contamination is avoided. There is no established routine inspection of the ERYC or EA permissions to drill.
Paragraph 9.4.3 of the report to planning
committee refers to the need “to protect the groundwater resource”
(Page 347). Since 12th May 2014 the Protectors at Crawberry Hill have
effectively protected the groundwater resource. Now that Rathlin have
regained access to the site there is an immediate risk to the
groundwater from drilling chemicals and radioactive waste unless the
required safety precautions relating to groundwater leakage from the
site are dealt with.
In addition monitoring arrangements are
clearly not effective and not coordinated. This is why we request an
agreement between East Riding of Yorkshire Council, Yorkshire Water
and the Environment Agency about the regularity of inspection visits
and a published timetable. In addition, given the vulnerability of
the aquifer we would also expect an undertaking to conduct
unannounced inspections with full public reports of the findings to
reassure residents.
3. Temporary Nature of the exploratory drilling in the Current Planning Permission
3.1 Temporary nature of exploratory drilling
There are numerous references to the temporary
nature of the exploratory drilling at Crawberry Hill in the report to
Planning Committee of 13th September 2012.
- The title of the report “Application for Construction of a temporary drilling site etc…” Page329
- Introduction –“a temporary well site” (Para 1.2 and 1.3 page 330)
- Case on behalf of the Applicant “proposing to construct a temporary well site” “The temporary development is required….”(Para 7.3 and 7.6 page 342)
- Recommendation. “The site preparation and construction, drilling and testing activities approved by this permission shall be carried out for a limited period of 24 months…
This condition is imposed because this is a
temporary permission to allow a period of exploration and testing.
(Para12.2 page 352)
- Reason for Decision “This development proposes a temporary well site for the purposes of testing for petroleum……”
“The development is considered acceptable
in landscape terms, subject to a temporary consent and full
restoration of the site.” (Page 360)
Rathlin may argue that they presented their
longer term objectives. In the Case on behalf of the Applicant
planning officers state, “If however, commercial quantities of
petroleum are present, then the applicant will suspend the well
pending the outcome of a decision on a subsequent planning
application for the production of petroleum.” ( Para 7.4, page 342)
It is clear that the full report did not
acknowledge this because of the repeated reference to the temporary
nature of the exploratory work and the special time limit of 24
months instead of the normal three years.
In any case elected members supported the
recommendations and this is recorded in the Notice of Decision.
Reason for Decision “This development
proposes a temporary well site for the purposes of testing for
petroleum……”
“The development is considered acceptable
in landscape terms, subject to a temporary consent and full
restoration of the site.” (NOD 18th
September 2012. Page 9.)
3.2 Rathlin’s long term plans
A claim for possession of property was served
on Protectors resident at the wooden construction on the access road
to the drilling pad on Thursday 24th July 2014 following
occupation by a number of people which started on 13th
June 2014.
In the accompanying witness statement by Tom
Selkirk, Country Manager for Rathlin, it is stated,
“Rathlin has an option at any time to require the Second Claimant to grant Rathlin a lease of Crawberry Hill in order to construct and operate a long term production facility at Crawberry Hill. The lease would be for a term of 25 years with an option to renew for a further 25 years.” (Selkirk Para 9. Page 3)
The second claimant is Philip Ellerington, the
landowner, who corroborates this statement in his witness statement.
3.3 Summary
This was the first time that Rathlin’s
long term intentions and plans became public. The plan is consistent
with the stated strategy of the Canadian parent company, Connaught
Oil and Gas, which, in its website reported its licence to develop
oil and gas resources in the Humber Basin, claiming that potential
reserves could be similar to the North Sea.
Rathlin has never published the link between
the “temporary, exploratory” drilling sites at West Newton and
Crawberry Hill and the strategy for 50 years of gas production from
these proposed “production” sites.
Had these facts been known at the time of
initial public consultations it is certain that many more and
detailed objections would have been raised by individuals and local
town and parish councils.
This is why we are calling for a stop to the
present planning permission which was based on a lack of full,
relevant information.
Also, there can be no doubt that it is in
the public interest for East Riding of Yorkshire Council to ensure
full formal consultation before any decision about the extension of
planning permission for a further 2 years.
4. Traffic Management
4.1 The Traffic Management Plan
Extensive consultation took place with the East
Riding Traffic Management team, the local Police and Parish Councils
about traffic to the drilling site. Local residents frequently drew
attention to the need to avoid vehicle traffic through adjacent
villages.
Rathlin provided a traffic management plan
which achieved minimal impact on local roads and villages by ensuring
that all traffic was directed to approach and leave the site by the
route running east towards Killingwoldgraves roundabout on the A1079.
To ensure this a sign was erected to indicate No Right Turn at the
site exit.
This sign and the traffic management plan has
been ignored by all tanker convoys visiting the site.
The No Right Turn sign has been removed by ERYC
staff.
Two way traffic is in place on the road and it
is therefore urgent to establish that the Traffic Management Plan is
adhered to before deliveries to the site are resumed.
“Development shall be carried out in accordance with the Approved Traffic Management Plan.” NOD 12.page5)
This requirement will become all the more
important once large convoys of supply lorries and equipment bring
drilling and equipment onto the site. It will be extremely important
when tanks containing acids and other chemical travel to the site;
similarly local residents will want reassurance about the safe
arrangements for transport by large numbers of tankers with
radioactive waste on board.
4.2 Summary
East Riding of Yorkshire Council must ensure that the agreed Traffic Management Plan is put in place before any resumption of activity on site by Rathlin.
Please acknowledge receipt ... but note that each of the signatories below wish to receive written
confirmation of receipt and an urgent response from you.
Thank you for your attention.
Yours sincerely,
[12 residents from the surrounding area]
No comments:
Post a Comment