The location of Rathlin Energy's proposed new well, West Newton B is:
Crooks Lane about 1 mile East of Burton Constable Hall and 0.625 miles South of West Newton.
Yorkshire Post article here:
Friday, 7 November 2014
Wednesday, 5 November 2014
Rathlin plan a new well - West Newton B
Some residents local to West Newton recently received the letter below inviting them to an information session.
It says Rathlin are preparing a Planning Application for another exploration well- West Newton B.
Presumably this is because they've had to abandon their 1st £8million well after a monumental cock up that meant after 4 months of trying and gas leaks, they finally gave up, having conducted none of their planned tests.
In the interests of balance locals decided to hold their own event through Frack Free East Yorkshire.
That'll be in the pub, at the same time.
It says Rathlin are preparing a Planning Application for another exploration well- West Newton B.
Presumably this is because they've had to abandon their 1st £8million well after a monumental cock up that meant after 4 months of trying and gas leaks, they finally gave up, having conducted none of their planned tests.
rathlininformationsession.eventbrite.co.uk
In the interests of balance locals decided to hold their own event through Frack Free East Yorkshire.
That'll be in the pub, at the same time.
Community Event
Monday, 27 October 2014
Nature: Fracking Unlikely to Reduce Greenhouse Gas Emissions
Some people (including local MP Graham Stewart) have said that because burning natural gas produces less CO2 emissions than burning coal (a notoriously filthy fuel) that fracking could help in the fight against climate change.
However, it seems likely that this would not be the case, according to this article that has just been published in Nature:
However, it seems likely that this would not be the case, according to this article that has just been published in Nature:
Limited impact on decadal-scale climate change from increased use of natural gas
Thursday, 23 October 2014
EA Letter to West Newton Local Residents
This letter was sent to residents who live very close to the West Newton well site, where serious problems with the well continue. Testing that should have been completed weeks ago hasn't even begun, and well intervention equipment is still present on site this week.
The letter states that the noxious smells that have been emanating from West Newton have stopped.
This is not the case. The smells continue to be reported.
We also note that the EA state,
The letter states that the noxious smells that have been emanating from West Newton have stopped.
This is not the case. The smells continue to be reported.
We also note that the EA state,
Monitoring results will be sent to Public Health England to check that any emissions do not have the potential for effecting public health.Which exposes as a lie Rathlin's claim that the smells are not harmful- they can not possibly know that. Rathlin don't even know exactly what the smells are, and have proved themselves incapable of controlling them.
Thursday, 2 October 2014
East Riding Council stifles democracy by excluding public from controversial planning meeting
In what seems like a deliberate attempt to stifle democracy, East Riding of Yorkshire Council is regularly excluding some members of the public from controversial planning meetings.
Planners met at Beverley County Hall this afternoon to discuss the Crawberry Hill well site planning application, which was know in advance to be controversial and have a large public interest.
So they chose to limit public access to just 40 people, and only allow them access to the gallery where it is impossible to see the speakers and difficult to hear.
More than that number again were outside the building demanding access, but were refused entry.
A formal request was submitted immediately prior to the meeting notifying them of the situation and requesting adjournment to a bigger room, but this was not even acknowledged.
Kayte White is a local resident from Newbald, just a few miles from the development and was left stood on the pavement outside while the meeting proceeded inside:
"Several of us from the village are here and have not been allowed in- we're shocked and absolutely appalled. This directly effects us and we have a right to see what goes on. They must have known this would happen, and there needs to be provision for this situation."
Richard Howarth from Frack Free East Yorkshire said:
"This is a shocking attempt to exclude members of the public who have a right witness these proceedings. This is supposed to be a democratic country and it's important democracy is seen to be done. In other areas of the country it is standard practice to find a bigger room- but East Riding Council are stuck in the past, and it's simply unacceptable.
The situation inside wasn't much better. The few people who did manage to get in all complained that they couldn't see what was going on, and couldn't hear properly- it was an absolute joke."
Minutes from ERYC Planning minutes (available here) show that the average number of members of the public attending is over 40 people. Controversial developments regularly attract far more.
Cherry Burton Village survey- 94% opposed to fracking
Hydraulic fracturing
(fracking) survey results
Cherry Burton
September 2014
Question:-Do
you support hydraulic fracturing?
Responses
Yes 2 4%
No 45 94%
Don’t
Know 1 2%
Comments
(reproduced verbatim)
Yes:
- none received
Don’t Know:-
One received
1) I am confused with the
different information in newspapers and TV from both the fors and
against. We need more info told in simply terms.
No:-
Thirteen received.
1) Several countries have
banned fracking due to environmental problems. It is not safe.
2) We are concerned about the water supply, which comes
directly from the Wolds. Fracking can
cause contamination.
Could it also cause
long term subsidence?
3) Fracking will
industrialise the countryside and increase traffic, disrupting rural
communities and farming conveyance. (Cause earthquakes?) Fracking
could contaminate water aquifers and soil causing danger to the
health of the public, crops, livestock and wildlife. If so
……. Contamination would occur by contact ingestion and
inhalation of chemical leakage. Effects:- Possible rejection of East
Riding crops and livestock – farmers loss! Possible boycott of
the Tourist Industry Possible water shortage Probable
drop in property value Probable defacement of the beautiful
countryside Maybe friends, family, visitors and guests would
avoid the area. Major Questions:- What about the
disposal of the poisonous waste water/chemical
solution/suspension? Where and how would it be stored?
The Future Generation ---- what for them?
4) We are concerned about
the environmental impacts, the pollution of water supply and the
potential of earthquakes as a result of fracking. I don’t feel it
is a safe viable alternative to our energy demands (as a nation).
5) House
prices will go down
Houses
will be uninsurable
Water
pollution
Can Yorkshire water
guarantee water aquifer contamination will not occur? And Rathlin.
Financial
guarantees to compensate should polluting occur.
Earthquakes!!!
Countryside
destroyed.
6) Rathlin Energy do not
get back to you on the telephone number that they have published on
their leaflets and do not follow up messages on their message box. So
what are they hiding?
7) Grave concerns over contamination of water courses.
Concerns
about resultant earth tremors
A small land mass such as
Great Britain is totally unsuitable for negative effects of fracking.
8) All the risks are ours
and with very little benefit!
There
are a number of concerns but my main concern is that if things go
wrong we have to live with the consequences. There is no way of
reversing such things as
a) Contaminate aquifers
b) Sink holes/earthquakes
c) Loss of property
values etc etc.
If
drilling and fracking go ahead, only the energy companies win. We
should have continuing payments into local coffers not 1 off
payments.
9) If it’s been banned
in various European countries and several states in America, there
has to be cause for doubt.
Despite
much talk, no-one seems to be able to say that this process is
completely safe – apart from those with a commercial interest.
Hardly reassuring!
10) Should do it out at
sea and use the sea water.
11) Can we have honest
answers to questions not rhetoric?
What effect will it
have on groundwater, both levels and quality?
What effect will it
have on aquifers?
Will additional
water in ground affect land stability, especially under houses, land
inclines eg hills?
If so much extra
water is being pumped into the ground, won’t it be less able to
absorb rain from the torrential flood type rain that we now
experience on a regular basis
(take this summer for
instance)?
12) Only in so far as 1)
reservations re water supply
2) Long term developers plans. Lack of
detail/transparency
Compiled by Cherry Burton Against Fracking
Survey forms available to
view.
Newbald Village survey: 96% opposed to fracking
This survey was posted through every door in the village of Newbald.
Respondents were able to leave optional
comments about their views on Fracking, of the 51 respondents 28
people felt strongly enough to add comments. All comments have been
duplicated below.
Comments in Favour of Fracking
“Advanced
civilisation needs energy, and gas is far cleaner than coal. More gas
available = less coal; less oil and coal imports, plus less
dependency on undemocratic states that supply the UK with gas. More
energy = more competitive and jobs for my sons.”
Comments against Fracking
“The
health and lives of the people living in East Yorkshire will be
adversely affected.”
“The
potential risk of water contamination is too high”
“VERY
concerned about this issue and frustrated that that we seem unable to
stop it happening”
“fear
of damage to aquifer and water pollution”
“mining
/drilling always in the long run affects ground water”
“I
am opposed to fracking for shale gas because, 1.As a country we
should not be looking for new sources of fossil fuels but alternative
greener sources of energy and 2. we should not be supporting ANY
PROCESS such as fracking which has, ANY POTENTIAL to poison both
surface and ground water supplies as well as risking air and soil
pollution.”
“I
am concerned about the health implications of this industry which
have been seen in other countries which have fracking. We need to ban
this like Germany and France have.”
“Not
happy about potential contamination of water supply; not happy about
damage to landscape
I
feel very strongly about this. I am well informed about the matter
and have researched both in favour of and against fracking. My
decision to be against is an informed decision.”
“Not
enough research being done into risk of damage to chalk aquifer, try
it and see not sensible approach, Who will manage security of wells
once shale gas is removed and the developers move on?”
“I
oppose Hydraulic Fracturing in East Yorkshire”
“We
are worried that is might affect our water and wildlife. We are both
dead against fracking and don't want it to go ahead.”
“Nice
little earner for those involved, but I cannot believe that it is
without risk in terms of subsidence or to the water supply. Also
there is the clutter to consider.”
“Poisoning
our water course, our children , ourselves will lead to destruction
of our area, which is beautiful and currently a healthy place to
live. Stop Fracking, put recourse into sustainable renewable energy.”
“strongly
disagree. I have done several online campaigns, I also filled in gov
campaign and got many of my facebook contacts to do so, really
worried about water supply and wonder why this has been banned in
many countries! why are we doing this in the uk! so short sighted of
councils everybody needs to think of the effect on the surrounding
varea as it will affect everyone. what about house insurance and de
valuing our beautiful village!!”
“I
have concerns about contamination of water supply, the impact on
wildlife and the fracking sites spoiling the look of our beautiful
countryside”
“I
do not support Fracking near Newbald as I am concerned about the
impact on our water supply and on the local wildlife.”
“banned
in usa,germany,france for health risks environmental reasons”
“it
appears to us that if fracking goes ahead we will be left with a
dangerous mess to clean up. lets all do as much as we can before this
happens”
“grave
environmental and health risks,industrialised landscape,loss of
tourism, house prices falling,its time to favour renewables or
catastrophic climate change is a real possibility.”
“I
fear for the health implications that are unknown in the already
fracked areas in the world. The industry is not tried and tested.”
“It
is in principle wrong to expand the use of fossil fuels as a source
of energy. They are all on balance associated with negative long term
consequences. Alternatives need to be developed. I do, however, find
the antifracking movement shrill and hypocritical and rather immature
in its approach. The same people objecting to fracking because of the
putative dangers and its antidemocratic implementation also object to
the expansion of windfarms in the area. Fracking needs to be seen in
the overall context of UK energy policy. It is only reasonable to
object to both fossil fuels and green energy if you can at the same
time promote an alternative. We need to encourage people to use less
energy overall, and to use the energy that they have to consume as
efficiently as possible. I want the taxes that I pay to be used not
to support the private sector to increase fossil fuel consumption, or
the inefficient production of energy from wind turbines, but to
subsidise energy saving and cheap green energy production. So - my
taxes should go towards subsidising home insulation projects;
preventing the loss of household energy to the environment; the
adoption of solar panels by private households; public transport etc.
In addition, private individuals and corporations should be penalised
severely for wasting energy if such waste is avoidable. Also, private
households should be provided a good price (an incentive) for
diverting their surplus solar energy into the national grid - energy
companies shoudl not get this energy on the cheap. Choose wisely
grasshopper.”
“I
don't think we know enough about the concequences of Fracking and I
am concerned about the implications this could have on our children's
lives”
“Worried
about the future for my grandson”
“I
am most concerned about contamination to drinking water through
leaked chemicals into our aquifer.”
“scared
of the risk of pollution to potable water sources and the
industrialisation of our countryside”
“I
believe fracking will damage our water supply and is unnecessary.”
Tuesday, 30 September 2014
Application to inject waste liquid into the North York Moors - COMMENT NOW
An insane plan to inject waste mining liquids into the North Yorkshire moors, of all places.
The applications are now open for comments... so let's get writing.
The applications are now open for comments... so let's get writing.
Ebberston Moor South – Planning Application Briefing
Wednesday, 24 September 2014
Planning Report Fails to Consider Comments - Formal Complaint
Rathlin have controversially applied to extend their planning permission at Crawberry Hill well site for another 2 years, but East Riding Planning Dept is so under resourced that it has been unable to add many comments to the public case file.
The deadline for comments was 11th Sept, and many locals went to the trouble of having their say, but a week and half later many comments had still not been processed and were not available to read on the planning website.
Despite this, the draft planning report for committee, which meets next Thurs 2nd Oct, was completed this morning.
This is crucial- as it seems that the report can't consider all the comments, nor the public scrutinise them.
For example, one comment from a neighbouring farm complains about noise from the site- a material consideration that must be taken in to account.
But the Environmental Health officer states, "residents ... confirm that they had no grounds to complain". This statement directly contradicts the residents comment- but the only reason we as the public became aware of it was because it was published accidentally.
The following formal complaint has been submitted:
__________________________________________________
The deadline for comments was 11th Sept, and many locals went to the trouble of having their say, but a week and half later many comments had still not been processed and were not available to read on the planning website.
Despite this, the draft planning report for committee, which meets next Thurs 2nd Oct, was completed this morning.
This is crucial- as it seems that the report can't consider all the comments, nor the public scrutinise them.
For example, one comment from a neighbouring farm complains about noise from the site- a material consideration that must be taken in to account.
But the Environmental Health officer states, "residents ... confirm that they had no grounds to complain". This statement directly contradicts the residents comment- but the only reason we as the public became aware of it was because it was published accidentally.
The following formal complaint has been submitted:
__________________________________________________
Monday
22/9/2014
To: Peter Ashcroft, Head
of Planning and Development Management, East Riding of Yorkshire
Council, County Hall, Beverley, HU17 7AT
Dear Mr.
Ashcroft,
Formal
complaint – lack of due diligence in the public consultation for
planning application 14/02622/STVAR
We write
to complain about the insufficient resourcing of the Planning
Department which means that public scrutiny of the statutory public
consultation with regards to planning application 14/02622/STVAR has
been prevented. In addition it is clear that you are not able to
arrange appropriate scrutiny by officers and elected members to
ensure due diligence and care is in place to protect the interests of
East Riding residents.
We emphasise
that this is no way a complaint about Shirley Ross, the individual
planning officer concerned who, despite an unacceptable workload, has
remained polite and helpful when dealing with our enquiries.
Many of
those concerned about the public consultation process have been
concerned that their objections submitted by the deadline of 11th
September 2014 have not yet appeared on the relevant website showing
associated documents for the 14/02622/STVAR application. Having
waited over a week to check that our objections were shown on the
website we contacted Shirley Ross this morning, 22/09/2014.
She
explained that workload meant that she had not been able to read,
check and upload the objections. She was concentrating on writing the
report. She hoped to upload the remaining letters of objection “by
the end of the week”. She pointed out that she had other reports to
write as well and was doing the best she could in the circumstances.
- How can Shirley Ross achieve due diligence on behalf of the ERYC with such a workload?
- For example how can she draft an accurate report if she has not been able to read and assess all the objections before writing it?
- How can she pass on new objections to the applicant in time for them to provide appropriate responses?
We pointed
out that in one case the published response of your senior
Environmental Health Officer, Ian McKechnie, was deliberately
misleading. He stated,
“I have
also discussed noise issues with residents of nearby properties who
confirm that they had no grounds to complain during the drilling
phase.”
This is
directly contradicted by the objection from Mrs Hayward of Cold
Harbour Farmhouse, the nearest neighbour to the Crawberry Hill
drilling site. She writes,
“While
test drilling the site was very noisy, not just drilling noise, the
worst problem was at night when pipes would bang against each other.”
Had Mr. McKechnie discussed noise issues with neighbours before
writing his report he could not have written his response.
What is more
significant as evidence to support this complaint is that Mrs
Hayward’s objection was placed on the website in error because it
had not been checked first. We phoned Shirley Ross this morning
22/09/14 to check why Mrs. Hayward’s letter, which I read and
printed out last week, was no longer on the website and she confirmed
that 4 letters had been removed because they went on without being
checked first.
This train
of events confirms why your process is unfit for purpose.
Objectors
and supporters of the planning application are entitled to see all
the relevant documents. So are Elected Members, especially those
directly involved as local members or members of the Planning
Committee.
If your
normal process had been followed Mrs. Hayward’s letter would still
not be available on line and we would not have been able to write to
her or to Mr.McKechnie to point out that there was a direct
misrepresentation of a relevant material consideration in reaching a
decision on the application.
In addition,
the officer responsible for drafting the report would not be aware of
the need to get her facts checked on this issue, especially if the
Cold Harbour Farm objection was not seen by her until after the
report was printed for the Planning Committee.
In summary,
we have presented evidence that, without being able to read all the
letters of objection and support and the responses from relevant
agencies and ERYC officers, it is not possible to exercise our
democratic right, as residents, to scrutinise information sent in by
the deadline of 11th
September 2014. In addition officers, including you, and Elected
Members do not have the information to enable scrutiny and checks to
ensure a proper process is in place and due diligence is being shown
by all concerned.
We have been
informed by Liz Russell on behalf of Diane Hindhaugh that the report
to the Planning Committee must signed off by you by the morning of
Wednesday 24th
September in order to be on the website by that afternoon to allow
the required 5 working days before the Planning Committee of 2nd
October 2014.
It is clear
that due to insufficient resourcing of the officer team you cannot
ensure that all responses received by the deadline of 11th
September 2014 can be checked and analysed so not all relevant
material considerations can be assessed in time to meet the deadline
of 24th September.
It does not
appear that you have any alternative but to postpone the report to
the next Planning Committee meeting so that a proper process of
drafting can be completed.
Yours
sincerely,
Friday, 5 September 2014
Chair of Rathlin also a chair of CPRE (Campaign to Protect Rural England) - and sees no conflict of interest
You couldn't make it up.
David Montagu-Smith, Chair of Rathlin Energy, the oil & gas company intent on industrialising the East Riding, is also Chair of CPRE West Northamptonshire District- a group that claims to Campaign to Protect Rural England.
This may go some way to explaining the group's enthusiasm in campaigning against wind turbines, with industrial Dave personally writing this letter on the group's behalf, thanking an MP for asking for wind subsidies to cut.
One member of CPRE has spoken out, as she believes he helped shape the organisation's policy on fracking.
Funniest of all, Smith himself seems utterly oblivious to the conflict of interest and, "is quite certain that the countryside has nothing to fear from the work of the oil industry...".
You can read Rathlin's Statement here.
David Montagu-Smith, Chair of Rathlin Energy, the oil & gas company intent on industrialising the East Riding, is also Chair of CPRE West Northamptonshire District- a group that claims to Campaign to Protect Rural England.
This may go some way to explaining the group's enthusiasm in campaigning against wind turbines, with industrial Dave personally writing this letter on the group's behalf, thanking an MP for asking for wind subsidies to cut.
Vested interests? Surely not! |
Funniest of all, Smith himself seems utterly oblivious to the conflict of interest and, "is quite certain that the countryside has nothing to fear from the work of the oil industry...".
You can read Rathlin's Statement here.
Wednesday, 3 September 2014
Fracking Industry found Guilty of Scaremongering
A fracking company, so quick to accuse their opponents of scaremongering, have been found guilty by the Advertising Standards Authority of misleading the public when it made unsubstantiated claims about the benefits of fracking and claimed a gas shortage put the UK close to catastrophe.
Monday, 25 August 2014
Tuesday, 19 August 2014
Planning Breaches: Reply from the council
This is a reply to this letter.
_________________________________
Crawberry Hill Drilling Site, Walkington
I refer to your e-mail dated 4 August 2014 addressed to Nigel Pearson, Chief Executive regarding planning consent ref. 12/02945/STPLF granted 18 September 2012 for the above site. I have been asked to respond on the Chief Executive’s behalf. This response also deals with concerns over the site’s fencing and lighting that have been raised in subsequent correspondence on 6 August and your e-mail dated 15 August asking to cease operations on the site and for all the agencies to work together.
Your letter requested that East Riding of Yorkshire Council immediately investigate “breaches of the planning conditions detailed in the Notice of Decision, report to the Planning Committee and in the meantime stop any test drilling at Crawberry Hill until –
i) Rathlin give proof that they are fully compliant with planning conditions, and
ii) A detailed monitoring regime and schedule of inspection visits by the ERYC, Yorkshire Water and the Environment Agency is agreed and published.”
The specific issues that your letter raised will be dealt with in turn below but the Council is satisfied that the planning conditions are being complied with, apart from the traffic management plan which will be explained below.
The Council, Yorkshire Water and the Environment Agency each have different remits and therefore will undertake their own monitoring visits to the site. The Council works with both Yorkshire Water and the Environment Agency but cannot prescribe when they should undertake their monitoring visits to the site.
Regarding Unconventional High Volume, High Pressure Hydraulic Fracturing
The permission is expressly for a temporary appraisal borehole to investigate the potential presence of petroleum minerals. Condition 15 expressly prohibits hydraulic fracturing activity. The approved Crawberry Hill exploratory operations do not propose hydraulic fracturing and the planning application did not seek to obtain permission to undertake such an operation.
Any agreement between Rathlin Energy and the Landowner has no bearing whatsoever on whether hydraulic fracturing is intended to be carried out at the site. The Council cannot comment on the allegation concerning Mr Ellerington’s repossession of his land as that is a civil matter between him and the developer.
Groundwater Management
Regarding the alleged breaches of condition 5.9 and 5.10;
Condition 5.9:
There shall be no discharge of foul or contaminated drainage from the site into either the groundwater or any surface waters, weather direct or via soakaways.
Condition 5.10:
Any facilities, above the ground for the storage of oils, fuels or chemicals shall be sited on an impervious base and surrounded by impervious walls. The volume of the bunded compound should be at least the equivalent capacity of the tank plus 10%. All filling points, vents, gauges and sight glasses must be located within the bund. The drainage system of the bund shall be sealed with no discharge to any watercourse, land or underground strata. Associated pipe work should be located above ground and protected from accidental damage. All filling points and tank overflow pipe outlets should be detailed to discharge into the bund. Such facilities shall be constructed and completed in accordance with plans approved by the Local Planning Authority.
Although there is no bund to the eastern boundary of the wellsite, there is a perimeter drainage system under the site which is provided to capture all surface water that migrates through the stone on to the membrane. The wellsite has been specifically constructed in a manner such as to prevent any contamination to the underlying subsoils and neighbouring fields.
A tank installed in the northeastern corner of the site, which was intended to receive surplus surface run-off water from the drainage ditch, is leaking. It was installed to provide additional surface water containment, in the event that Rathlin Energy was unable to bring water tankers to the wellsite to reduce the water level in the perimeter drainage ditch. The tank was subsequently identified as having a leak so Rathlin Energy closed the inlet valve and declared the tank unsuitable for use. Samples of the surface run-off water were obtained and sent away for analysis.
The content of the tank is believed to have been only surface run-off water, but this cannot be confirmed as Rathlin Energy were unable to access the wellsite for a period due to the site being occupied by protestors. The tank has now been mended.
Alleged lack of routine monitoring
The planning conditions relating to protecting water resources were attached at the request of the Environment Agency. This was at a time prior to the introduction of their permitting regime for such works. The Environment Agency confirmed to the Council that the changes to the regulatory regime since the planning application was approved mean that those activities at Crawberry Hill now fall under the Environmental Permitting Regulations and they are regulated under the permit issued by the Environment Agency on the 2 May, 2014. The Environment Agency has confirmed to this Council’s officers that they are satisfied that the proposal meets the requirements of condition 5 and the site will continue to be monitored under the permit. Whether or not the activity on site is in breach of the environmental permit is a matter for enforcement by the Environment Agency.
Temporary permission
The letter refers to the temporary nature of the exploratory drilling at Crawberry Hill. The planning permission is a temporary permission for 24 months (see Condition 2 of the planning permission). The Council has received an application (14/02622/STVAR) from Rathlin Energy for a variation of that planning condition that seeks to allow for a further 24 months to complete operations relating to exploration and testing at the Crawberry Hill site. The Council has invited comments on the application in the usual manner and the application will be considered by the Council's Planning Committee in due course following the expiry of the consultation period.
Rathlin’s long term plans
As with any company exploring for minerals, Rathlin Energy remain hopeful that petroleum will be encountered in commercial quantities during its exploratory operations in the East Riding of Yorkshire. These intentions have been made clear from the outset both in the planning application and in the extensive public consultations they have undertaken, pre- and post- planning permission being granted. Should the exploratory operations prove unsuccessful in finding commercial quantities of petroleum, the well will be plugged and abandoned with site restoration being undertaken thereafter, in accordance with the terms of the planning consent.
The agreement between Rathlin Energy and the Landowner provides initially for a temporary occupation, consistent with the temporary period applied for in the planning application, covering only the planned exploration activities. The 2012 permission grants a temporary exploratory permission. The developer’s strategy, whether publicised or not, does not alter that. Any future consent would be a matter of public consultation.
Traffic Management
The traffic management plan has not been adhered to as access to the Crawberry Hill wellsite became difficult due to the presence of protesters. In order to facilitate Rathlin Energy going about its business, Humberside Police have instructed Rathlin Energy to access the wellsite using an alternative route to that approved under the traffic management plan, primarily down to safety reasons. Whilst the road ‘Walkington Heads’ is a live and active road even on occasions when it has closures in place, the paramount priority is to get vehicles onto the site whilst maximising people’s safety, including the safety of the workers, police and protestors. To bring a large long convoy of vehicles past the tents and structures that are in place on land forming part of the highway, the police have had to look at alternative routes, in order to maximize safety. When accessing the site, a police escort is provided to ensure the safety of other road users, Rathlin Energy employees and the protestors. The planning condition was imposed in the interest of highway safety, but the police have amended the approved routeing arrangements in the interests of highway safety based on a different scenario than that envisaged during the planning process, I consider it would not be expedient or in the public interest for the Council to take enforcement action.
Fencing
Rathlin have erected a steel security fence. Prior to its erection they checked details of the fencing with the Council. The Council confirmed that the site would have permitted development rights regarding fencing under the General Permitted Development Order. The fence will need to be removed at the end of the temporary consent under the site restoration works.
Lighting
The Council’s Public Protection department, who requested the condition regarding lighting be attached to the planning consent, have confirmed that they are not concerned by the lighting on the site based on the information in your letter. If there is a serious road safety concern about lighting affecting traffic, then this is a matter for the Police. Public Protection can investigate alleged light nuisance, but it would need to be the occupant of a neighbouring property who complained about the lighting and how it affected them at their property, not in the street. Nonetheless it is understood that the lighting rig on site has been adjusted to reduce its impact on the public highway.
I hope you find the above helpful. I will copy this letter to all addresses of your e-mail of 4 August 2014 for their information.
Yours sincerely
Alan Menzies Director of Planning & Economic Regeneration
Planning Breaches: Letter to Council
The reply to this letter is here.
_________________________________
To: Chief Executive
East Riding of Yorkshire Council
Dear Mr. Pearson,
We the
undersigned request that as the responsible planning authority,
the East Riding of Yorkshire Council immediately investigate the
breaches of the planning conditions detailed in the Notice of
Decision, report to the Planning Committee and in the meantime
stop any test drilling at Crawberry Hill until -
i) Rathlin give proof that they are fully compliant with planning conditions and ii) A detailed monitoring regime and schedule of inspection visits by the ERYC, Yorkshire Water and the Environment Agency is agreed and published. (References: Report to the Planning Committee ERYC 13th September 2012 Application for Construction of a temporary drilling site etc 12/02945/STPLF, and Notice of Decision, Town and Country Planning Act, 1990, |
1.Background to the this request
Unconventional High Volume, High Pressure Hydraulic Fracturing known as Fracking
1.1 Fracking at Crawberry Hill
A specific condition of the planning permission was included following representations from local residents,
15.Hydraulic fracturing (also known as “hydro-fracking” or “fracking”) is expressly not permitted under the development hereby approved.The condition is imposed in the interests of groundwater protection and the broader protection of the amenities of residents. (NOD Condition 15)
However, in a later application to the
Environment Agency submitted by Rathlin Energy UK Ltd on 16th
January 2014 it is stated that as part of the test drilling Rathlin
will
“inject liquids into the well….. for “well stimulation” or “hydraulic fracturing” purposes..” (Section 9.4.5 page 10)
In addition Rathlin state
The activity on site relates to the exploration for hydrocarbons from the Crawberry Hill 1 wellsite. Specifically, this will involve perforation of the existing well-casing to perform tests within the Bowland Shale, Namurian Sandstone and Kirkham Abbey formations. These tests may require the injection of water, some of which may return to the surface. (EA 9.2.1 page 8)
This is a reference to the exploratory
hydraulic fracturing of the Bowland shales used elsewhere in the UK
by companies such as Cuadrilla or I-gas who are open about their
search for shale gas in the same Bowland shales.
Mr Ian Crane, with 20 years experience as a
senior executive in the oil industry, is ready to give evidence that
the Bowland shales are known to be “tight”. Like similar gas
shales in the USA where fracking has been used extensively, gas can
only be extracted by hydraulic fracturing for testing and production
purposes.
Further understanding of Rathlin’s intentions
may be gained from the current installation of fracking pumps at the
West Newton test site.
In contrast to the statements by Rathlin as
part of public consultation and subsequently, the papers submitted by
Rathlin to the High Court hearing of 29th July 2014
included the lease agreement with Philip Ellerington which states
“Rathlin has an option at any time to require the Second Claimanat to grant Rathlin a lease of Crawberry Hill in order to construct and operate a long term production facility at Crawberry Hill. The lease would be for a term of 25 years with an option to renew for a further 25 years.”(Witness statement of Tom Selkirk. 22/07/2014. Para.6. Page 2. Copy attached)
Rathlin are not currently testing, including
the use of fracking, at Crawberry Hill but intend to do so now they
have possession of the site. They are therefore not currently in
breach of Condition 15 but are making preparation to do so.
Given the emerging data and analysis of long
term serious health impacts from fracking in the USA and the detailed
reports of the failure of hydraulic fracking at Preese Hall in 2011
we urge a review of the planning permission given to Rathlin because
of the risks posed to residents of the East Riding and refer to our
European Convention Human Right Article 8.
2. Groundwater Management
2.1 Breach of Planning Conditions 5.9 and 5.10
Condition 5.9. States
“There shall be no discharge of foul or contaminated drainage from the site into either the ground water or any surface waters, whether direct or via soakaways.” ( NOD page3)
Condition 5.10. States
“The drainage system of the bund shall be sealed with no discharge to any watercourse, land or underground strata. Associated pipework should be located above ground and protected from accidental damage. All filling points and tank overflow pipe outlets should be detailed to discharge into the bund.” (NOD page3)
The attached photograph shows there is no bund
on the eastern boundary of the main drilling site so if we experience
a severe weather event similar to recent storms in nearby Cottingham
or Market Weighton there would be a high probability of run-off onto
the pea and wheat crops in adjacent fields.(Attached A.0)
The photographs also show leakage from the
storage tank used to receive surplus water from the drainage ditches
on the drilling pad.(Attached 1-5) This leaks into a very small bund
around the tank which does not meet the specification of 110%
capacity of the tank.
While the current position is that rainwater is
likely to be the main run-off, the concern must be that without full
conformity with the planning permission and regular monitoring by the
planning authority (ERYC) , the Environment Agency and Yorkshire
Water, the commencement of drilling and testing does pose significant
risk to local crops and the aquifer.
The well testing will involve thousands of
gallons of hydrochloric acid and other chemicals. Rathlin’s
application to the Environment Agency acknowledges that drilling
fluids and any water released from deep underground by drilling will
be likely to contain Naturally Occurring Radioactive Materials
(NORMs) as well as solid radioactive scale from the equipment. It is
an obvious risk if spills and leaks mean that rainwater can wash
these contaminants onto farmland and into the aquifer.
(Such a spillage has already been reported
to Birds Eye, the buyer of the peas harvested at West Newton. Philip
Ellerington cites his contract with Birds Eye as the reason for
urgent repossession of his land in his High Court witness statement
dated 21/07/2014)
The Environment Agency, gave permission to
Rathlin to drill at Crawberry Hill on 2nd May 2014.
“These include a Permit (EPR/BB3000KC) for
mining waste operations at the wellsite, namely the management of
extractive waste from prospecting for mineral resources. The permit
also allows flaring of waste gas arising from onshore oil and gas
operations as Permit (PB3930DV) for disposal of radioactive waste.”
(Tom Selkirk. Witness statement 22/07/2014 Para 28. Pages 8 and 9)
Further detail about waste is given in
Rathlin’s application to the Environment Agency dated 16/01/2014.
9.2.1 How do you plan to accumulate radioactive waste?
The
activity on site relates to the exploration for hydrocarbons from
the Crawberry Hill 1 wellsite. Specifically, this will involve
perforation of the existing well-casing to perform tests within
the Bowland Shale, Namurian Sandstone and Kirkham Abbey
formations. These tests may require the injection of water, some
of which may return to the surface. Additionally, water naturally
present in the target formation has the potential to flow to the
surface. Contact with the target formations mean that waste
(produced water) may contain low levels of Naturally Occurring
Radioactive Material(NORM) and so accumulation of radioactive
waste is unavoidable. There is also potential for scales forming
within associated pipe network. The waste produced waters arriving
at the surface will be piped to a device which separate any
hydrocarbons present from the produced waters. The produced waters
will then be piped directly into, and accumulated in, dedicated
storage tanks, from which they are removed by road at suitable
intervals for disposal to an authorised waste disposal facility.
Equipment found to be contaminated with scales will be removed
from service and stored in a designated quarantine area to await
removal from site ( following characterisation).
|
The application goes on to request a maximum
storage period on site of 3 months while the waste is tested and
further indicates a maximum volume of waste storage of 125 cubic
metres.
(Crawberry Hill B9 Application Form
16/01/2014 9.2.2 and 9.2.3 page 8)
The volume of the current, leaking, storage
tank for groundwater is 24 cubic metres so Rathlin are requesting 5
similar storage tanks for radioactive waste.
2.2 Lack of routine monitoring at Crawberry Hill
The Protectors at Crawberry received a letter from Martin Christmas of the Environment Agency (attached A.1 ) and Mr Crane replied on the 22nd June ( attached A.2 ).
On the weekend of 19th-20th
July there was heavy rainfall. Mr Crane noted the water from the
drainage ditch on the well site was up to the level of the overflow
pipe. He opened the valve to drain some of the water in the ditch
into the overflow tank. It quickly became apparent that the 24 cubic
metre relief tank is not fit for purpose. The tank had a leak at the
base of the tank (photos attached A.3- A.5 ) and at the seal between
the overflow pipe and the tank.
Jon Mager contacted the Planning office on the
21st July to enquire about Crawberry Hill. He asked if the
case office, Shirley Ross, had visited the drilling site recently. He
was told that Mrs Ross was on leave and that the details of
monitoring visits were kept by her.
The water was leaking straight onto the soil so
Mr Crane shut off the overflow valve and tried to call Martin
Christmas at the Environment Agency. Martin Christmas returned the
call on the morning of Thursday 24th July (call recorded).
Having explained the situation regarding leaks Mr Crane invited him
to visit the Crawberry Hill site to conduct his own inspection;
Martin Christmas advised that he wasn’t too concerned because it
would only be rainwater.
On the 30th July Jon Mager contacted
Mrs Ross to catch up on planning issues on her return from leave. Mrs
Ross confirmed that she was responsible for monitoring but had not
visited for some while.
Mr Mager then outlined the concerns about
leaks; Mrs Ross replied that the Environment Agency carried out
regular checks and was surprised to be told that this was not the
case.
2.3 Summary
In summary Rathlin have not conformed to the strict conditions laid down to ensure that groundwater contamination is avoided. There is no established routine inspection of the ERYC or EA permissions to drill.
Paragraph 9.4.3 of the report to planning
committee refers to the need “to protect the groundwater resource”
(Page 347). Since 12th May 2014 the Protectors at Crawberry Hill have
effectively protected the groundwater resource. Now that Rathlin have
regained access to the site there is an immediate risk to the
groundwater from drilling chemicals and radioactive waste unless the
required safety precautions relating to groundwater leakage from the
site are dealt with.
In addition monitoring arrangements are
clearly not effective and not coordinated. This is why we request an
agreement between East Riding of Yorkshire Council, Yorkshire Water
and the Environment Agency about the regularity of inspection visits
and a published timetable. In addition, given the vulnerability of
the aquifer we would also expect an undertaking to conduct
unannounced inspections with full public reports of the findings to
reassure residents.
3. Temporary Nature of the exploratory drilling in the Current Planning Permission
3.1 Temporary nature of exploratory drilling
There are numerous references to the temporary
nature of the exploratory drilling at Crawberry Hill in the report to
Planning Committee of 13th September 2012.
- The title of the report “Application for Construction of a temporary drilling site etc…” Page329
- Introduction –“a temporary well site” (Para 1.2 and 1.3 page 330)
- Case on behalf of the Applicant “proposing to construct a temporary well site” “The temporary development is required….”(Para 7.3 and 7.6 page 342)
- Recommendation. “The site preparation and construction, drilling and testing activities approved by this permission shall be carried out for a limited period of 24 months…
This condition is imposed because this is a
temporary permission to allow a period of exploration and testing.
(Para12.2 page 352)
- Reason for Decision “This development proposes a temporary well site for the purposes of testing for petroleum……”
“The development is considered acceptable
in landscape terms, subject to a temporary consent and full
restoration of the site.” (Page 360)
Rathlin may argue that they presented their
longer term objectives. In the Case on behalf of the Applicant
planning officers state, “If however, commercial quantities of
petroleum are present, then the applicant will suspend the well
pending the outcome of a decision on a subsequent planning
application for the production of petroleum.” ( Para 7.4, page 342)
It is clear that the full report did not
acknowledge this because of the repeated reference to the temporary
nature of the exploratory work and the special time limit of 24
months instead of the normal three years.
In any case elected members supported the
recommendations and this is recorded in the Notice of Decision.
Reason for Decision “This development
proposes a temporary well site for the purposes of testing for
petroleum……”
“The development is considered acceptable
in landscape terms, subject to a temporary consent and full
restoration of the site.” (NOD 18th
September 2012. Page 9.)
3.2 Rathlin’s long term plans
A claim for possession of property was served
on Protectors resident at the wooden construction on the access road
to the drilling pad on Thursday 24th July 2014 following
occupation by a number of people which started on 13th
June 2014.
In the accompanying witness statement by Tom
Selkirk, Country Manager for Rathlin, it is stated,
“Rathlin has an option at any time to require the Second Claimant to grant Rathlin a lease of Crawberry Hill in order to construct and operate a long term production facility at Crawberry Hill. The lease would be for a term of 25 years with an option to renew for a further 25 years.” (Selkirk Para 9. Page 3)
The second claimant is Philip Ellerington, the
landowner, who corroborates this statement in his witness statement.
3.3 Summary
This was the first time that Rathlin’s
long term intentions and plans became public. The plan is consistent
with the stated strategy of the Canadian parent company, Connaught
Oil and Gas, which, in its website reported its licence to develop
oil and gas resources in the Humber Basin, claiming that potential
reserves could be similar to the North Sea.
Rathlin has never published the link between
the “temporary, exploratory” drilling sites at West Newton and
Crawberry Hill and the strategy for 50 years of gas production from
these proposed “production” sites.
Had these facts been known at the time of
initial public consultations it is certain that many more and
detailed objections would have been raised by individuals and local
town and parish councils.
This is why we are calling for a stop to the
present planning permission which was based on a lack of full,
relevant information.
Also, there can be no doubt that it is in
the public interest for East Riding of Yorkshire Council to ensure
full formal consultation before any decision about the extension of
planning permission for a further 2 years.
4. Traffic Management
4.1 The Traffic Management Plan
Extensive consultation took place with the East
Riding Traffic Management team, the local Police and Parish Councils
about traffic to the drilling site. Local residents frequently drew
attention to the need to avoid vehicle traffic through adjacent
villages.
Rathlin provided a traffic management plan
which achieved minimal impact on local roads and villages by ensuring
that all traffic was directed to approach and leave the site by the
route running east towards Killingwoldgraves roundabout on the A1079.
To ensure this a sign was erected to indicate No Right Turn at the
site exit.
This sign and the traffic management plan has
been ignored by all tanker convoys visiting the site.
The No Right Turn sign has been removed by ERYC
staff.
Two way traffic is in place on the road and it
is therefore urgent to establish that the Traffic Management Plan is
adhered to before deliveries to the site are resumed.
“Development shall be carried out in accordance with the Approved Traffic Management Plan.” NOD 12.page5)
This requirement will become all the more
important once large convoys of supply lorries and equipment bring
drilling and equipment onto the site. It will be extremely important
when tanks containing acids and other chemical travel to the site;
similarly local residents will want reassurance about the safe
arrangements for transport by large numbers of tankers with
radioactive waste on board.
4.2 Summary
East Riding of Yorkshire Council must ensure that the agreed Traffic Management Plan is put in place before any resumption of activity on site by Rathlin.
Please acknowledge receipt ... but note that each of the signatories below wish to receive written
confirmation of receipt and an urgent response from you.
Thank you for your attention.
Yours sincerely,
[12 residents from the surrounding area]
Subscribe to:
Posts (Atom)